5.10 Overview of performing an overwrite installation in a cluster system

To perform an overwrite installation of JP1/IT Desktop Management 2 in a cluster system, perform an overwrite installation on the primary server first, and then on the standby server.

To perform overwrite installation in a cluster system:

  1. Take the service resources of JP1/IT Desktop Management 2 on the primary server offline.

    For details about the service resources to be taken offline, see the JP1/IT Desktop Management 2 service resources (generic services) row in the table listing the resources that must be registered in groups. You can find the table in 2.10.2 Procedure for creating a group resource on the primary server. The IP address resource, network name resource, and shared disk (physical disk) resource remain online.

  2. On the primary server, perform an overwrite installation of JP1/IT Desktop Management 2 - Manager.

  3. Start setup on the primary server to upgrade the database.

    If you do not need to upgrade the database, you can skip this step.

  4. Copy the file that is output when setup finishes on the primary server to the standby server.

  5. Move the owner of the group resource to the standby server.

  6. On the standby server, perform an overwrite installation of JP1/IT Desktop Management 2 - Manager.

  7. Start setup on the standby server to upgrade the database.

    If you do not need to upgrade the database, you can skip this step.

  8. Move the owner of the group resource to the primary server.

  9. Bring online the service resource you took offline in step 1.

The process of performing the overwrite installation in a cluster system is complete.