6.3.6 Linking the schedule rules of the upper-level jobnet
To link the schedule rules of the upper-level jobnet with a nested jobnet:
-
In the JP1/AJS3 - View window, in Function Menu, click Schedule Definition.
Schedule Definition is now selected.
-
In the list area, click the root jobnet of the jobnet for which you want to define a schedule.
The root jobnet you clicked is now selected.
-
Choose Edit and then Edit, or double-click the root jobnet.
The Jobnet Editor window appears.
-
In the tree area of the Jobnet Editor window, click the target jobnet and choose Edit and then Schedule.
The Schedule Settings dialog box appears.
-
Deselect Depends on upper-level jobnet.
-
In Schedule rules, click the Add button.
The Schedule Rule dialog box appears.
-
Make definitions in Rule number and Rule number to link.
- Rule number
-
Specify the rule number.
- Rule number to link
-
Specify the rule number of the upper-level jobnet with which the schedule rules are to be associated.
-
Click the OK button.