6.7.2 Setting the completed-action linkage function

The completed-action linkage function automatically changes the status of monitoring objects according to the JP1 event handling status.

This function simplifies Central Scope operations because it changes the status of monitoring objects according to the JP1 event handling status, thereby eliminating the need to change the status of monitoring groups manually.

In JP1/IM - Manager that has been installed as a new installation, this setting is initially enabled. In JP1/IM - Manager that has been installed as an upgrade installation, the same setting that was specified in the previous version is initially retained. You should change the setting as appropriate to your operation.

To set the completed-action linkage function:

  1. Terminate JP1/IM - Manager.

  2. Execute the jbssetcnf command using one of the following files as the argument as appropriate:

    To enable the completed-action linkage function: action_complete_on.conf

    To disable the completed-action linkage function: action_complete_off.conf

    When you execute the jbssetcnf command, the setting is applied to the JP1 common definition information.

    For details about the jbssetcnf command, see the JP1/Base User's Guide.

    About the setting in the file:

    For details about the setting in the file, see Settings file for the completed-action linkage function (action_complete_xxx.conf) in Chapter 2. Definition Files in the manual JP1/Integrated Management 2 - Manager Command, Definition File and API Reference.

  3. Start JP1/IM - Manager.