Hitachi

JP1 Version 12 JP1/Automatic Job Management System 3 Operator's Guide


12.7.5 Change Priority dialog box

The Change Priority dialog box changes the priority of jobnet execution. The following figure shows the Change Priority dialog box.

Figure 12‒202: Change Priority dialog box

[Figure]

The following explains the displayed items.

Jobnet name

Displays the name of the jobnet to be changed.

Priority

In the Priority dropdown list, specify the priority of jobnet execution. You can set None, or 1 to 5. The highest priority is 5. The default is the priority preset for the jobnet.