Hitachi

JP1 Version 12 JP1/Automatic Job Management System 3 Operator's Guide


12.7.4 Change Delay Monitor Temporarily dialog box

The Change Delay Monitor Temporarily dialog box sets how to monitor a jobnet delay. The following figure shows the Change Delay Monitor Temporarily dialog box.

Figure 12‒201: Change Delay Monitor Temporarily dialog box

[Figure]

The following explains the displayed items.

Jobnet name

Displays the name of the jobnet whose delay monitor method is to be changed.

Base time

Displays the base time for the job group containing the jobnet.

Scheduled start time

Displays the scheduled start time of the specified jobnet.

Scheduled end time

Displays the scheduled end time of the specified jobnet.

Delayed start

Specify this when monitoring the delayed start of the jobnet. The default is the previously set monitoring method. The monitoring method you can specify is different between the root jobnet and a nested jobnet. You can select one of the following items:

  • Do not monitor

    Does not monitor the delayed start.

  • Absolute time

    Specify the absolute time when the monitoring of the delayed start is started.

    You can set 0 to 47 for the value of hours and 0 to 59 for the value of minutes. By default, the hours before change and the minutes before change are applicable.

  • Relative from start of root jobnet

    Specify the relative time from the scheduled start time of the root jobnet for the specified jobnet.

    Note that the relative time is when the monitoring of delay is started.

    For the root jobnet, you cannot specify this item.

  • Relative from start of upper-l jobnet

    Specify the relative time from the scheduled start time of the upper-level jobnet for the specified jobnet.

    Note that the relative time is when the monitoring of delay is started.

    For the root jobnet, you cannot specify this item.

  • Relative from start of the jobnet

    Specify the minutes since the scheduled start time of the specified jobnet passed until the monitoring of delay is started.

    You can set 1 to 2,879 for the value of minutes. By default, the minutes before change are applicable.

Delayed end

Specify this when monitoring the delayed end of the jobnet. The default is the previously set monitoring method. You can specify one of the following monitoring methods.

  • Do not monitor

    Does not monitor the delayed end.

  • Absolute time

    Specify the absolute time when the monitoring of the delayed end is started.

    You can set 0 to 47 for the value of hours and 0 to 59 for the value of minutes. By default, the hours before change and the minutes before change are applicable.

  • Relative from end of root jobnet

    Specify the relative time from the scheduled end time of the root jobnet for the specified jobnet.

    Note that the relative time is when the monitoring for a delay starts.

    For the root jobnet, you cannot specify this item.

  • Relative from end of upper-l jobnet

    Specify the relative time from the scheduled end time of the upper-level jobnet for the specified jobnet.

    Note that the relative time is when the monitoring for a delay starts.

    For the root jobnet, you cannot specify this item.

  • Relative from end of the jobnet

    Specify the minutes since the scheduled end time of the specified jobnet passed until the monitoring for a delay starts.

    You can set 1 to 2,879 for the value of minutes. By default, the minutes before change are applicable.

Monitoring jobnet

When using jobnet execution time to monitor the end of the jobnet, select Time-required-for-execution and specify the time required for execution for the jobnet in minutes. You can specify 1 to 2,879. By default, the contents defined in the Define Details dialog box appear.