7.2 Re-executing a jobnet

You can re-execute jobnets whose execution has been completed, such as a jobnet whose detailed definition is corrected.

Prerequisites

The following explanation assumes that the execution of the jobnet has been ended abnormally.

Procedure

  1. In the JP1/AJS3 - View window (Main window), in function menu area, select Status Monitor.

    [Figure]

  2. In the tree area, select the job group. In the list area, select the jobnet.

    To help you understand the next step, the following describes the Status and Result columns in the JP1/AJS3 - View window (Main window).

    Status

    Displays the current status of the jobnet.

    If the jobnet is executed according to a predefined schedule (planned execution) and has a subsequent execution schedule, a status for which the next execution is being waited for, such as Wait for start time, is displayed. If the jobnet is executed immediately, Not sched. to exe. is displayed because no next execution schedule exists.

    Result

    Displays the execution results of the last executed jobnet.

  3. Select Operations, and then Rerun.

    The Generation Selection dialog box appears.

  4. Select Result.

    [Figure]

    In the above dialog box, Status and Result indicate Status and Result columns in the list area in the JP1/AJS3 - View window (Main window).

    Select Status to re-register the jobnet that will be executed in planned execution.

    Select Result to re-execute the last executed jobnet.

    Because you need to re-execute the last executed jobnet, select Result.

  5. Click the OK button.

    The Rerun dialog box appears.

  6. In Rerun method, select the unit from which to re-execute the jobnet.

    [Figure]

  7. Click the OK button.

    The Rerun dialog box closes, and then the jobnet is re-executed.

  8. Wait a while, and then select View, and then Refresh.

    The list area in the JP1/AJS3 - View window (Main window) displays the re-execution results.

Result

The operation was restored by re-executing the jobnet that ended abnormally.