Job Management Partner 1 Version 10, Job Management Partner 1/Automatic Job Management System 3 Operator's Guide

[Contents][Glossary][Index][Back][Next]

15.7.5 Change Priority dialog box

The Change Priority dialog box changes the priority of jobnet execution. The following figure shows the Change Priority dialog box.

Figure 15-189 Change Priority dialog box

[Figure]

The following explains the displayed items.

Jobnet name
Displays the name of the jobnet to be changed.

Priority
In the Priority dropdown list, specify the priority of jobnet execution. You can set None, or 1 to 5. The highest priority is 5. The default is the priority preset for the jobnet.