8.2 When a UAP or utility execution takes too long

Executor: HiRDB administrator

When the processing time of a UAP or utility takes longer than expected, an operation command should be used to check the execution status of the UAP or utility. Figure 8-4 shows the procedure for checking UAP or utility execution status.

It must be noted that the execution status of the following utilities cannot be checked using the procedure shown in Figure 8-4:

For these utilities, the pdls -d prc command can be used to check only whether processing by the utility is underway.

Figure 8-4 Procedure for checking the UAP or utility execution status

[Figure]