17.8.3 Starting and stopping during planned node switching in the 1-to-1 node switching system of Application Server

This subsection describes the procedure for switching the executing node and standby node of 1-to-1 node switching system in Application Server in cases other than those where an error has occurred. When you are switching nodes, Application Server in the standby node host must be in the standby state.

  1. From the Start menu, select Control Panel - Performance and Maintenance - Management Tools, and then select Cluster Administrator.

    The Cluster Administrator starts.

  2. In the console tree (left pane), select the resource group that contains the executing node and standby node, and then from the File menu, choose Migrate Group.

    The nodes switch.