Hitachi

JP1 Version 12 JP1/IT Desktop Management 2 Configuration Guide


3.11 Procedure for changing the currency unit

This is a management server setup item.

You can change the currency unit you use for asset management.

To change the currency unit:

  1. Log on to the OS as a user with administrator permissions.

  2. On the Windows Start menu, select All Programs, JP1_IT Desktop Management 2 - Manager, Tools, and then Setup.

  3. In the Setup window, click the Next button.

  4. In the Select a Setup view, select Settings Modification, and then click the Next button.

  5. Continue to click the Next button until the Other Settings view opens.

    [Figure]

  6. In the Currency Unit Setting section, enter a value in Currency Unit, and then click the Next button.

  7. In the Confirm Setup Settings view, check the settings, and then click the Next button.

    A dialog to confirm that Remote Install Manager and JP1/IT Desktop Management 2 - Asset Console are not being used is displayed. After confirming, click the OK button. In the cluster system, make the cluster resources associated with the services displayed in the dialog offline, and then click the OK button.

  8. In the Setup for Distribution by Using Remote Install Manager view, click the OK button.

    The setup process begins, and a dialog box appears indicating that setup is in progress. When setup has finished, the Setup Complete view appears.

  9. In the Setup Complete view, click the OK button.

The currency unit is changed.