Hitachi

JP1 Version 12 JP1/Integrated Management 2 - Manager Messages


KAVB0551-E

The number of accumulated response-waiting events on the manager exceeded the maximum (2000).

The oldest response-waiting event on the manager was released from the hold-and-accumulate state because the maximum number of response-waiting events that can be accumulated on the manager was exceeded.

S:

Continues processing.

O:

Check the integrated trace log of the manager, and then take the corrective action given for the KAVB1801-E message, which indicates that the response-waiting event was released from the hold-and-accumulate state.

After the corrective action is completed, restart the notification function for monitoring of the accumulation state in the Event Console window so that a notification is issued if the maximum number of response-waiting events that can be accumulated is exceeded again.