4.6.1 Overview of calendar information

This subsection provides an overview of JP1/AJS3 calendar information and describes the options available in JP1/AJS3 - Definition Assistant to modify calendar information.

Organization of this subsection

(1) Calendar information

In JP1/AJS3, open days and closed days can be defined as part of the jobnet execution schedule to create a calendar for JP1/AJS3 operation.

You can set calendar information by using the Edit Monthly Calendar window or Edit Annual Calendar window in JP1/AJS3 - View and by editing the calendar definition information section of the definition information management template in JP1/AJS3 - Definition Assistant. For details, see 5.1.1(7) Calendar definition information section.

In JP1/AJS3 - Definition Assistant, you can load calendar information by using the import function and apply the information by using the export function.

Figure 4‒28: Importing and exporting calendar information in JP1/AJS3 - Definition Assistant

[Figure]

(2) Options available to modify calendar information

The calendar definition information section of the definition information management template allows you to modify calendar information in JP1/AJS3 - Definition Assistant. Specifically, either enter the option corresponding to the modification you want to make in the first row of the applicable cell or append the option to the applicable date under the Open day or Closed day heading, and then use the F2 key to mark the cell you have just edited. The information inside the marked cell is applied when Change export is performed to export modified definition information.

The following table describes the options available to modify the calendar definition information section (cells under the Open day and Closed day headings).

Table 4‒11: Options available to modify the calendar definition information section (cells under the Open day and Closed day headings)

No.

Description of modification

Information to be set in the applicable cell(s)

Details of how to use the option

Date

Option

1

Add a date corresponding to either an open day or a closed day.

Date to be added

Not specified

4.6.2(1)

2

Delete a date corresponding to either an open day or a closed day.

Date to be deleted

:X (Appended to the date in question)

4.6.2(2)

3

Delete all calendar information corresponding to the specified date (date to be deleted) and all days preceding it.#1

Date to be deleted

:D (Appended to the date in question)

4.6.2(3)

4

Delete all calendar information.#2

Not specified

:C (First row)

4.6.2(4)

#1

Information defined in the unmarked calendar information cell (cell under the Open day or Closed day heading) is also deleted (that is, the unmarked cell is affected by the update performed by Change export). If there is definition information you want to retain, you have to mark the cell containing the values you want to retain.

#2

Information defined in the unmarked calendar information cells (cells under the Standard week, Open day, and/or Closed day headings) is also deleted (that is, these cells are affected by the update performed by Change export). If there is definition information you want to retain, you have to mark the cells containing the values you want to retain.