A communication timeout occurred during the communication with the service (service-name).: maintenance-information

A communication timeout error occurred during communication with the service indicated in service-name.

(S)

Cancels command execution.

For the queueless cluster process, the system cancels the processing to attach the logical host. Then, by default, the system continues startup processing without abnormally terminating the queueless cluster process.

If you want to abnormally terminate the queueless cluster process, specify error for the AJSQL_CLUSTERREQ environment setting parameter.

For details about AJSQL_CLUSTERREQ, see 20.10 Setting up the queueless job execution environment in the JP1/Automatic Job Management System 3 Configuration Guide.

If the processing to detach the logical host has been canceled, the system abnormally terminates the queueless cluster process.

(O)

A timeout might have occurred due to high load on the network or machine. Use Task Manager in Windows or the top command or another means in UNIX to check the status of the network and machine. Then re-execute the command that resulted in the error.

If the error occurred when the queueless cluster process was being started, restart the JP1/AJS3 service.

If the error occurred when the queueless cluster process was being stopped, execute the ajsqldetach command to detach the logical host that caused the error.

If you cannot correct the problem by taking the above actions, contact the system administrator, and then collect data (see 1.2.3 To the system administrators).