12.3.30 Add dialog box (for a nested jobnet or job)

The Add dialog box (for a nested jobnet or job) is used to specify the start time of the next execution schedule or fixed execution schedule for a jobnet. The following figure shows the Add dialog box.

Figure 12‒57: Add dialog box (for a nested jobnet or job)

[Figure]

The following explains the displayed items.

Unit name

Displays the name of the unit to which a start time is added.

Start time of upper jobnet

Lists the start times for the upper-level jobnet. From the list, select the start time for the upper-level jobnet to be added to Unit name.

Start time

Specify the start time for the next execution schedule or fixed execution schedule.

The following table lists the values that you can set and default values.

Table 12‒17: Specifiable values and defaults

No.

Time

Specifiable value

Default

1

Year

1994 to 2036

Current year

2

Month

1 to 12

Current month

3

Day

1 to 31 (Number of days in the month)

Current day

4

Hours

0 to 47

Current hour

A blank for the Monthly Schedule window

5

Minutes

0 to 59

Current minutes