13.5.5 Synchronizing monitoring settings after backing up and restoring PFM - Manager or JP1/SLM
If you back up and restore JP1/SLM or PFM - Manager, you must manually synchronize their respective monitoring settings.
To synchronize monitoring settings:
-
Start PFM - Manager.
-
Start JP1/SLM and log on.
-
Update the configuration information in the JP1/SLM Configuration information settings window.
Synchronize the configuration information and monitoring items between PFM - Manager and JP1/SLM.
-
This step is required only when restoring JP1/SLM. Check the monitoring settings and whether monitoring is ON or OFF in the JP1/SLM Monitor settings window.
Check the following:
-
Monitoring (ON or OFF) of monitoring items
The node color indicates ON or OFF. Make sure that:
Nodes that are supposed to be ON are not set to OFF.
Nodes that are supposed to be OFF are not set to ON.
-
Monitoring settings for monitoring items:
Make sure that the threshold values and predictive error detection settings for ON nodes are correct.
-
-
In the Start/Stop monitor window, synchronize the monitored status (Start or Stop) and monitoring settings with PFM - Manager.
Set as follows according to whether each service is being monitored:
-
Service being monitored
Start service monitoring and update PFM - Manager with the latest monitoring settings in JP1/SLM.
-
Service not being monitored
Stop service monitoring and stop monitoring by PFM - Manager.
-
For details on the JP1/SLM operations, see the manual Job Management Partner 1/Service Level Management.