Hitachi

Job Management Partner 1 Version 10 Job Management Partner 1/IT Desktop Management 2 Distribution Function Administration Guide


9.5.4 Forcibly completing a split distribution job

Forced completion is to suspend a split distribution job, and transfer the remainder of the package in a single transfer. To forcibly complete a split distribution job, select Execute, and then Forcibly Complete Split Distribution in the Job Status window. The forcibly completed job is transferred from a system directly under the system to the distribution destination system, in a single transfer without splitting (normal distribution). Note that forced completion of split distribution applies to only the split distribution jobs on all the systems under a system that executed the forced completion. Note also that a suspended job or resuming job cannot be forcibly completed.

If you want to forcibly complete split distribution only on a relay manager/system directly under the system, and want to execute split distribution for distribution destination systems under the relay manager/system, execute the same package with a Transfer package to relay system job. The split distribution to the relay manager/system is forcibly completed (the package is normally distributed), but the package is split distributed to the distribution destination systems under the relay manager/system.