KAVV351-E
When you add a planning group or a jobnet that is directly under a planning group to a schedule, you can only perform fixed registration specified with a fixed schedule period.
You cannot add the planning group and the jobnet directly under the planning group to a schedule.
- (S)
-
Cancels processing.
- (O)
-
To add a schedule, do the following for the jobnet directly under the planning group.
- When adding a schedule based on the existing schedule:
-
Register the jobnet for fixed execution with a new schedule period specified.
- When adding a single schedule independent of the existing schedule:
-
Add the jobnet to the next schedule in the Change plan field.
You cannot cancel changes in the added schedule. To cancel the changes, you must cancel the execution.