2.3.5 Changing the contents of the Processing_Of_Received_Order jobnet registered for execution
This section describes how to use the Jobnet Monitor window to re-execute jobs from the Job_CheckStock job that ended abnormally.
The procedure explained here assumes that all the operations in 2.3.4 Monitoring the Processing_Of_Received_Order jobnet during execution are completed. You also need to eliminate the cause of the job that ended abnormally. For this example, you must prepare the C:\Temp\stock-check file so that the Job_CheckStock job ends normally. You do not need to write anything in the stock-check file.
To re-execute the Processing_Of_Received_Order jobnet:
- In the JP1/AJS3 - View window, in Function Menu, make sure that Status Monitor is selected.
- In the tree area, make sure that the AJSROOT1 job group is displayed. In the list area, click the Processing_Of_Received_Order jobnet.
The Processing_Of_Received_Order jobnet is now selected.
- Choose View, Jobnet Monitor, and then Result.
The Jobnet Monitor window appears.
- In the map area, click the icon of the Job_CheckStock job.
The icon of the Job_CheckStock job is now selected.
- Choose Operations and then Rerun.
The Rerun dialog box appears.
- Define the first job to be executed.
Define the following in the Rerun dialog box.
Figure 2-20 Rerun dialog box
![[Figure]](FIGURE/ZUV02160.GIF)
- Unit name
- Check that Job_CheckStock is displayed.
- Rerun Method
- Select From this unit.
- Click the OK button.
The Rerun dialog box closes.
The Job_CheckStock job is re-executed and its icon is displayed in green, indicating that the job is being executed. When the Job_CheckStock job ends normally, the Job_CreateReceivedOrderSlip job begins to be executed. Normal termination of the Job_CreateReceivedOrderSlip job completes the processing of the Processing_Of_Received_Order jobnet.
- Supplementary note
- If the execution schedule and execution status do not appear, click View and then Refresh to update the window display.