Job Management Partner 1/Automatic Job Management System 3 Overview
You can add an execution schedule to a root jobnet, specifying an execution start date and time. This is possible only for a jobnet that is registered for fixed execution or not scheduled to execute.
Also, you can add an execution schedule to a nested jobnet that is subordinate to a root jobnet that has already been scheduled for execution.
- Organization of this subsection
- (1) Adding an execution schedule to a root jobnet
- (2) Adding an execution schedule to a nested jobnet
(1) Adding an execution schedule to a root jobnet
When you add an execution schedule, it is added as a fixed execution schedule. Any schedule definitions that were specified for the nested jobnets or the root jobnets are ignored from this point. Also, start conditions for jobnets are not monitored, and jobnets with start conditions are executed immediately. When there are nested jobnets defined under the root jobnet to which you have added the execution schedule, the nested jobnets inherit the same scheduled execution time as the root jobnet.
You can perform this operation using either the GUI or the ajsentry command. For details on using the GUI, see 9.2 Adding an execution schedule for a jobnet in the Job Management Partner 1/Automatic Job Management System 3 Operator's Guide. Alternatively, for details on the ajsentry command, see the description of ajsentry in 2. Commands in the manual Job Management Partner 1/Automatic Job Management System 3 Command Reference 1.
(2) Adding an execution schedule to a nested jobnet
You can add an execution schedule to a nested jobnet that is subordinate to a root jobnet that has already been scheduled for execution. However, you cannot add an execution schedule to a nested jobnet that has already been scheduled for execution. The units in the nested jobnet to which an execution schedule is added are scheduled as described below.
- Jobnet that has been registered for fixed execution
Because the jobnet has already been scheduled, the execution schedule is added only to the nested jobnet additionally specified.
- Jobnet that has been registered for planned execution when the schedule depends on the upper-level unit
The execution schedule is also added to the units that are subordinate to the nested jobnet additionally specified.
- Jobnet that has been registered for planned execution when the schedule does not depend on the upper-level unit
The schedule is recalculated and re-created.
You can add an execution schedule to a nested jobnet from the GUI or by the ajsplan command. For details on the GUI operations, see 9.2 Adding an execution schedule for a jobnet in the Job Management Partner 1/Automatic Job Management System 3 Operator's Guide. For details on the command operations, see the ajsplan in 2. Commands in the manual Job Management Partner 1/Automatic Job Management System 3 Command Reference 1.